Stato Avanzamento Lavori
Submitted by Anonymous (not verified) on Thu, 11/19/2009 - 04:48In reply to A newbie all over again! by Annec
Lollita. Thank you. You're
Submitted by Noddy on Thu, 11/19/2009 - 07:16In reply to A newbie all over again! by Annec
In reply to A newbie all over again! by Annec
This is the equivalent to a UK "valuation" or stage payment. It should not, subject to what your contract may say, imply any acceptance. You should normally have a % retention (5%?) which you hold until you are satisfied all the works are completed to your satisfaction